Among the many documents accompanying a construction project, the site work diary is one of the most neglected — and, quite often, the party most harmed by that neglect is the very party who neglected it. A review of the case law shows that the courts show no leniency towards this default.

The Normative Basis: from Statutory Duty to Professional Standard

In the past, the duty to keep a work diary was regulated by regulation 6(3) of the Planning and Building Regulations (Supreme Supervision of Construction), 5752-1992. When those regulations were repealed at the end of 2016, the question arose whether the legal basis for the duty had fallen away. The case law answered in the negative — the repeal of the regulation did not abolish the professional expectation.

CC (Herzliya Mag.) 21849-07-17 Oni Aref v. Elazra Yozma VeHashkaot Ltd. (2019)

The Evidentiary Consequence: an Unkept Diary Is a Double-Edged Sword

In the absence of documentation, it was held that "there is no evidence that the construction works were carried out with the due diligence expected of a reasonable contractor", and that this default "is capable of attesting to the defendants' negligence". The "missing evidence" rule was also applied: the failure to produce the diaries gave rise to a presumption that, had they been produced, they would have operated against the party who withheld them.

CC (Central Dist.) 42023-03-13 Representation of the Condominium at 6 HaBad St. v. Kalash Mordechai Nechasim (2019); CC (TA Mag.) 9168-03-20 Hartuv Levy Ltd. v. Israel Electric Corporation (2025)

Delays and Additional Works: the Diary as an Evidentiary Anchor

The two most common disputes in construction projects are: who is responsible for the delay in the schedule, and who approved the additional works. A properly kept work diary provides a direct answer to both. It has been held that a diary kept unilaterally, without the other party's signature, is admissible in evidence, provided the entries were made contemporaneously.

CC (Nazareth Mag.) 33753-01-18 Yona Peer v. Miron (2023); CC (TA Mag.) 1506-09-18 Mana Contracting Co. v. Mahajna Ali Abu Raad (2024); Insolvency Case (Haifa Dist.) 381/01 Ma'as Pladot Binyan v. Official Receiver (2025)

The work diary is not a bureaucratic form — it is a defence document. A contractor who fails to keep a proper diary may discover in court that its absence has become the strongest evidence against him.